The short answer
We remodeled both restrooms in a Bethesda office suite over three weekends. The crew replaced the tile, partitions and fixtures, added ADA grab bars, and handed the space back each Monday morning ready to use.
The problem
The suite still had its original tile, cracked partitions and fixtures that leaked. The tenant could not close the restrooms during the work week.
What we did, step by step
Weekend one: demo and rough plumbing
Old tile, partitions and fixtures came out and the supply lines were replaced.
Weekend two: tile and partitions
New porcelain floor and wall tile went in, followed by powder-coated partitions.
Weekend three: fixtures and inspection
Touchless faucets, new toilets and ADA grab bars were installed and inspected.
How long it took
Three weekends, start to finish. Each phase was finished by Sunday evening so both restrooms worked on Monday.
The tricky part
Building management only allowed contractor work on weekends, so every phase had to end with working restrooms.
The result
Both restrooms reopened on schedule with new tile, touchless fixtures and ADA-compliant grab bars.